Private prototype. Facts from research on 2 to 3 October 2026; not yet reviewed for publication. Forms do not submit.
Council said no - overruledIver, Buckinghamshire

Iver said no. Ministers said yes.

Buckinghamshire Council refused a data centre on the old Woodlands Park landfill in Iver. In July 2025 the Government overruled it. A legal challenge followed, and the Government accepted its decision should be quashed. What happens next is still unclear.

Planning notice
Woodlands Park data centre, Iver
Ref
APP/N0410/W/24/3347353
Decides
Secretary of State for Housing, Communities and Local Government
Size
22.15 ha
Next
Conditions and detailed plans
How you can help

We're not running a petition here while the legal position is settled. Sign up and we'll tell you when there's something you can do.

Why local people are worried

Green BeltThe site is Green Belt land next to the M25. Ministers called it 'grey belt' to let it through.
TwiceThe council refused a data centre here more than once. Local decisions keep being overridden.
PromisesThe developer's environmental promises need to be legally binding and enforceable.

It's approved. Here's what you can still do

The headline decision has been made, but conditions and detailed designs still need approval. Each is a chance to be heard.

  • Quote the reference: APP/N0410/W/24/3347353
  • Good planning grounds include: impact on the Green Belt or countryside, energy use and carbon, water supply, noise, traffic, wildlife and heritage. Developers' promises are not guarantees: ask for them to be made binding.

Read our full guide to objecting

Others campaigning here

We link to everyone working on this. Please support them too.

Spread the word

Every fact on this page is sourced. See the full record on Data Centre Watch. Last checked 3 October 2026.