Approved - but it's not overWaterton, Bridgend

Bridgend's data centre: ten buildings, one decision so far

Vantage has permission for a ten-building data centre campus on the old Ford engine plant at Waterton. Only the first building has full permission. Each of the other nine still needs approval.

Planning notice
Vantage Bridgend
Ref
P/25/247/HYB
Decides
Bridgend County Borough Council
Size
55 ha
Next
Sign-off and later phases
What we're asking for

To Bridgend County Borough Council: Every later phase of the Waterton data centre campus, and its temporary power plant, must come back to councillors in public, with real water and power figures.

Why local people are worried

392Backup diesel generators proposed across the campus.
10Data centre buildings, built in phases over years.
WaterWelsh Water said local supply capacity is limited, and upgrades are needed.

It's approved. Here's what you can still do

The headline decision has been made, but conditions, legal agreements and detailed designs still need approval. Each is a chance to be heard.

  • Quote the reference: P/25/247/HYB
  • Good planning grounds include: impact on the Green Belt or countryside, energy use and carbon, water supply, noise, traffic, wildlife and heritage. Developers' promises are not guarantees: ask for them to be made binding.

Comment on each reserved matters application via Bridgend CBC's planning portal and ask local councillors to call them to committee.

Read our full guide to objecting

Others campaigning here

We haven't found a local group yet. If you're organising, get in touch and we'll link to you, or hand this page over.

Spread the word

Every fact on this page is sourced. See the full record on Data Centre Watch. Last checked 3 October 2026.