Council said no - overruledPoyle and Colnbrook, Slough

Slough was overruled on Manor Farm

Slough Borough Council opposed a data centre on Green Belt land at Manor Farm, Poyle Road. In June 2026 the Government granted it permission anyway. Now a second, three-times-bigger data centre is planned right next door.

Planning notice
Manor Farm, Poyle Road, Slough
Ref
APP/J0350/W/25/3366043
Decides
Slough Borough Council for discharge of conditions
Size
72MW, 8.16 ha
Next
Conditions and detailed plans
How you can help

This one already has permission. The decision that's still open is next door: please add your name on the Manor Farm West page. Go to the Manor Farm West, Poyle (Slough) page.

Why local people are worried

47Diesel backup generators approved on the site.
Green BeltGreen Belt and Colne Valley Regional Park land, next to Heathrow.
Next doorA second scheme on the neighbouring field, Manor Farm West, would add another 216MW. Comments on it close on 20 October 2026.

It's approved. Here's what you can still do

The headline decision has been made, but conditions and detailed designs still need approval. Each is a chance to be heard.

  • Quote the reference: APP/J0350/W/25/3366043
  • Good planning grounds include: impact on the Green Belt or countryside, energy use and carbon, water supply, noise, traffic, wildlife and heritage. Developers' promises are not guarantees: ask for them to be made binding.

No open consultation on this permission. Comments on the connected Manor Farm West application can be made on Slough Borough Council's planning register, reference P/21160/000.

Read our full guide to objecting