Private prototype. Facts from research on 2 to 3 October 2026; not yet reviewed for publication. Forms do not submit.
Being built - more to decideCambois, near Blyth, Northumberland

Cambois: two buildings started, eight still to decide

QTS has permission for up to ten data centre buildings on the old Blyth Power Station site. Work has started on the first phase. Every later phase still needs approval from Northumberland's councillors.

Planning notice
QTS Cambois Data Centre Campus
Ref
24/04112/OUTES
Decides
Northumberland County Council
Size
720MW, 102 ha
Next
Later phases
What we're asking for

To Northumberland County Council Strategic Planning Committee: Don't approve any further phase at Cambois until QTS publishes real power, water and wildlife plans, and the combined impact of every data centre planned around Blyth is assessed.

Why local people are worried

1,100MWReported total site power for the full campus.
55Diesel generators per building in the first phase.
MoreTwo more data centre schemes are reported nearby, at West Sleekburn and Factory Road.

Have your say on the next phases

Later phases still need approval, and each one is a chance to be heard.

  • Quote the reference: 24/04112/OUTES
  • Good planning grounds include: impact on the Green Belt or countryside, energy use and carbon, water supply, noise, traffic, wildlife and heritage. Developers' promises are not guarantees: ask for them to be made binding.

Comment on the reserved matters applications through Northumberland County Council's planning portal while they are open (reference not captured); contact ward councillors and members of the Strategic Planning Committee.

Read our full guide to objecting

Others campaigning here

We link to everyone working on this. Please support them too.

Spread the word

Every fact on this page is sourced. See the full record on Data Centre Watch. Last checked 3 October 2026.