Approved - but it's not overNorth Weald Bassett, Essex

Google's North Weald data centre isn't signed off yet

Epping Forest councillors backed Google's data centre campus on North Weald Airfield in December 2025. The final permission still isn't issued, and the energy plan is still vague.

Planning notice
North Weald Airfield data centre campus
Ref
EPF/0849/25
Decides
Epping Forest District Council
Size
164MW, 21 ha
Next
Sign-off and later phases
What we're asking for

To Epping Forest District Council and Google: Don't finalise Google's North Weald permission until the energy plan is specific and legally binding: how much power, from where, and what it means for local bills and the climate.

Why local people are worried

164MWUp to two data centre buildings on the old RAF airfield.
EnergyHow much power, and from where, is still to be set out in a detailed energy strategy.
ObjectionNorth Weald Bassett Parish Council objected.

It's approved. Here's what you can still do

The headline decision has been made, but conditions, legal agreements and detailed designs still need approval. Each is a chance to be heard.

  • Quote the reference: EPF/0849/25
  • Good planning grounds include: impact on the Green Belt or countryside, energy use and carbon, water supply, noise, traffic, wildlife and heritage. Developers' promises are not guarantees: ask for them to be made binding.

Reserved matters applications will be consulted on by Epping Forest District Council. The condition changes and s106 are being finalised by officers, with no public committee vote identified.

Read our full guide to objecting

Others campaigning here

We link to everyone working on this. Please support them too.

Spread the word

Every fact on this page is sourced. See the full record on Data Centre Watch. Last checked 2 October 2026.