Early stageCambois, near Blyth, Northumberland

Three data centres round Cambois? Count them together

TBC Partners has asked Northumberland County Council whether a data centre of up to 300MW on about 12 hectares at Factory Road, Cambois, needs a full environmental assessment. It would be the third scheme lined up around Cambois, next to QTS's ten-building campus and the West Sleekburn plans.

Planning notice
Blyth Data Centre, Factory Road, Cambois
Ref
None yet
Decides
Northumberland County Council
Size
300MW, 12 ha
Next
Planning application expected
What we're asking for

To Northumberland County Council: Require a full environmental assessment for the Factory Road data centre, and count all three Cambois schemes together before anything more is approved.

Why local people are worried

300MWUp to 300MW, the developer says, on about 12 hectares.
ThirdQTS's campus and the West Sleekburn scheme are both close by.
EarlyIt's at the screening stage, the best time to insist on a full environmental assessment.

Get ready to object

There's no planning application yet, so there's nothing formal to object to. This is the time to get organised, tell the developer and councillors what you think, and be ready when the application goes in.

  • Good planning grounds include: impact on the Green Belt or countryside, energy use and carbon, water supply, noise, traffic, wildlife and heritage. Developers' promises are not guarantees: ask for them to be made binding.

No consultation is open on a screening request. If a full application is submitted, comment on the Northumberland County Council planning portal. Until then write to local councillors and MP Ian Lavery.

Read our full guide to objecting

Others campaigning here

We link to everyone working on this. Please support them too.

Spread the word

Every fact on this page is sourced. See the full record on Data Centre Watch. Last checked 3 October 2026.