Decision pendingNorth Ockendon and Upminster, Havering

No shortcut for 600MW on Havering's Green Belt

A 600MW data centre campus is proposed on Green Belt farmland at North Ockendon, through a fast-track planning order rather than a normal application. Havering's planning committee still has to decide whether to adopt it.

Planning notice
East Havering Data Centre Campus
Ref
None yet
Decides
London Borough of Havering, as local planning authority
Size
600MW
Next
Council decision, date not set
What we're asking for

To Havering Strategic Planning Committee: Don't adopt the East Havering data centre order. A 600MW campus on Green Belt farmland needs a full planning application and a decision in the open.

Why local people are worried

600MWReported total power demand for the campus.
ShortcutA Local Development Order would grant permission in one go, without a normal application.
Green BeltMetropolitan Green Belt farmland on the edge of London.

Object - it takes ten minutes

A formal comment to the planning authority counts for more than a petition. Say in your own words how this would affect you, and stick to planning grounds.

  • Good planning grounds include: impact on the Green Belt or countryside, energy use and carbon, water supply, noise, traffic, wildlife and heritage. Developers' promises are not guarantees: ask for them to be made binding.

Consultation has closed. Residents can contact Havering councillors on the Strategic Planning Committee, their MP, and watch the committee agenda on democracy.havering.gov.uk; further consultation is possible if the LPA makes significant changes

Read our full guide to objecting

Others campaigning here

We link to everyone working on this. Please support them too.

Spread the word

Every fact on this page is sourced. See the full record on Data Centre Watch. Last checked 2 October 2026.